Status of HRMS/CS 9.0 Upgrade
As of 3/29/2010
-
Functional Fit/Gap
- All Campus Solutions Fit/Gap sessions were completed on 12/15/09
- Spreadsheets containing customizations were received by UofL on 12/15/09, except Financial Aid which was received on 1/4/10
- Summary Documents received by UofL on 1/25/10
- All HRMS Fit/Gap sessions were completed on 12/3/09
- Spreadsheets containing customizations were complete by 12/15/09
- Summary Documents were received by UofL on 1/25/10
- Security Fit/Gap session was completed on 12/17/09
- Documents received by UofL on 2/3/10
-
First test move to production
- Database turned over for functional testing on 11/16/09 without maintenance
- Database turned over to functional users to test on 1/25/10, with maintenance as of 12/10/09
- Testing on Campus Solutions at 8%
- Testing on HRMS at 35%
-
Second test move to production
- Database turned over to functional user to test on 1/28/10, with maintenance as of 12/10/09
- Testing on Campus Solutions at 50%
- Testing on HRMS at 80%
-
Overall status on upgrade
- Customizations at 95% complete
- Overall testing percentages at 65%
- Estimating 2.5 weeks behind schedule
- Testing % by Module:
UGRD Admissions 45% GRAD Admissions 45% Campus Card 0% Campus Health 0% Financial Aid 45% Student Financials 35% Student Records 60 % Academic Advising 75 % Payroll 80% Position Management 85% Talent Acquisition 75% Benefits Admin. 75% Institutional Research 100% MySoft 100% Blackboard 0% Alumni Development 0% Miscellaneous 0% CAMS 0% -