What is the Plone 4 schedule?
Timeline
Item |
Completion Date |
Description |
Create Sandbox Area |
July 1, 2011 |
Testing Area For Customers |
Purchase Equipment |
December 9, 2011 |
Equipment has been identified and ordered. It takes 10 days for delivery. |
Install Equipment |
January 30, 2012 |
Installation and setup. |
Create Staging Area |
January 30, 2012 |
Staging area will be for Next Gen customer work and testers ONLY. This area may still have bugs and we will use it as a testing / development area until the production area is ready. |
Create Customer Training & Documentation |
July 1, 2012 |
Preliminary documentation will be completed and training will be available. Training will be made available for both site administrators and general users. |
OCM Marketing Plone 4 |
July 1, 2012 |
Create a marketing plan to the University community outlining the many advantages of Plone 4 |
OCM New Plone Templates |
July 1, 2012 |
Create multiple sets of templates using the new branding standards needed to support University departments. |
Configure Production Environment |
July 1, 2012 |
Launch for departmental use. |
Complete rebuild of sites. |
June 30, 2014 |
Shutdown of Plone 3 environment. |