PeopleSoft SAS/HRMS Implementation
Quarterly Report
January-March 1999
Milestones since December 1998
System deployment and implementation
-
Continued initial deployment specifications and user testing, data conversion
and interface installation for implementation
-
Continued functional testing in all modules
-
Met regularly with PeopleSoft and Cambridge Technology to oversee and
direct
upgrade strategy for PeopleSoft Version 7.5
-
Installed Version 7.5 of the PeopleSoft system
-
Installed and tested Version 7.5 database prepared at the PeopleSoft
upgrade lab
-
Moved Undergraduate Admission Pre-Applicants and Course Catalog to Version
7.5 production
-
Implemented Payroll for Version 7.5 production and began parallel testing
for first issue of ORION paychecks in May
-
Completed implementation of Financial Aid 7.5
-
Continued development of other modules in Version 7.5 for scheduled
implementation
-
Completed requisition and negotiation process for interactive
voice-response/TouchTone
system to work with PeopleSoft
-
Continued introductions to PeopleSoft system for academic and support
units
-
Attended the annual PeopleSoft Higher Education conference
Policy and operational issues
-
Continued frequent communication with all project sponsors, constituency
senates, and project stakeholders
Training and knowledge transfer
-
Began work on campus-wide introduction to the ORION system in production
-
Continued PeopleSoft training for technical and functional staff members
-
Continued training and system security work group for development and
implementation
of a campus-wide training program
-
Continued participation in PeopleSoft Higher Education special-interest
group
Staffing
-
Continued positive and constructive consulting arrangements with Cambridge
Technology Partners
-
Welcomed team member from the Office of Planning and Budget
Issues
-
The inelastic timeframe for implementation of modules continues to require
intensive, detailed project planning for appropriate use of staff
resources.
-
Timely receipt of system modifications and improvements from PeopleSoft
must be insured for scheduled implementation to be completed.
-
Unit staffing for production environment needs to be verified as end-user
training begins.
-
Space allocation for project staff and training rooms may need to be increased
in 1999.
Activities for April-June 1999:
-
Continue planning, design and data conversion activities to prepare for system
implementation
-
Complete and certify the results of the April payroll test run
-
Begin ORION paycheck printing and distribution (biweekly 5/14; monthly 5/30)
and retire the current system
-
Put Version 7.5 Financial Aid module into production
-
Convert Admissions and Student Records data for current students
-
Implement full Admissions processing
-
Implement Spring 2000 Schedule of courses
-
Install and implement IVR/Touch-tone system
-
Continue campus-wide training program for functional users
-
Continue timely review and resolution of policy and operation issues
-
Continue to develop and test Web applications to reduce client workstation
requirements on campus and to permit WWW facilities for financial aid,
registration, personal information update, and human-resources
requirements
Return to Project ORION home page.