PeopleSoft SAS/HRMS Implementation

 

Quarterly Report
January-March 2000


Despite detailed and extensive preparations, W2 printing in January was disrupted by continued issues of data and reporting accuracy, necessitating a general reissue of W2 forms at the end of February.  The processing of expense transfers, adjustments and reversals to budget accounts is still being addressed so that the system will provide detailed, accurate and complete account reports to unit business administrators and fiscal officers.  On the Student Administration side, work continues to coordinate Web access to the system, to insure correct charges, payments and reports through the TouchTone (interactive voice-response) system, and to provide full service for transcripts, grades, financial aid and residence administration requests.  To meet immediate needs, work on some modules (including transfer equivalencies and advising) has been postponed until after a new software release is installed at the end of this quarter.

Project ORION team members have worked with unusual dedication.  The urgency of the remaining work has taxed available staff resources to their limit.  The executive sponsors (the provost and the vice presidents for finance and administration, student affairs, and information technology) have therefore decided to expand the resource base by hiring Cambridge Technology Partners for an 8-week support project (beginning April 3) that adds these resources:  a CTP client partner, a project manager, 2 functional consultants and 1 technical consultant.  These additional resources will address remaining issues in the Payroll module; when those issues are resolved, the resources will be directed to support other areas of the project.

This change in resources will parallel a change in the overall project management, which will now be directly supervised by a project steering committee consisting of the executive sponsors and a campus liaison.  Policy issues that arise will be directed to the steering committee by the HR and SAS core teams.

The support of the campus community continues to be an important element of project success.  Campus questions and issues can be addressed to the project management at project.orion@louisville.edu.
 

Milestones since September 1999

Activities for April-June 2000: Posted 03/30/00