October-December 1997
-- Initiated public phase of the project with a kick-off luncheon for 300 project sponsors, team
members and campus community leaders
-- Identified two stages of the implementation, foundation and enrichment, to differentiate the
goals and objectives of the project's timeline
-- Established campus advisory committees
-- Implemented communications plan with WWW site and direct communication via team
minutes, campus-wide e-mail distributions, and individual e-mail Q&A through a PROFS service
account
-- Opened the project issues database for public review and comment via WWW to assure
systematic and open review of system issues
-- Began data administration discussions to standardize data coding structures across campus
-- Initiated workstation support team
-- Began and completed Scope phase 11/5-12/1
-- Began Business Process Prototyping using PeopleSoft Release 6.0, 12/1
-- Installed PeopleSoft Release 7.0
January-March 1998
-- Completed seventeen weeks of system prototyping for Human Resources and Student
Administration modules
-- Identified and began negotiating contract with the vendor for a new interactive voice response
(IVR)/Touchtone system
-- Examined data conversion and interface issues
-- Reviewed university-wide data administration and organized a group to oversee data integrity
-- Established a timeline and plan for student-administration data conversion from legacy systems
-- Initiated post-prototyping implementation planning process
April-June 1998
-- Completed initial prototyping for Human Resources and Student Administration modules
-- Completed transition to deployment (system specification and user testing)
-- Began system processing on SR70 server
-- Researched ancillary software support for e-mail and Web applications
-- Revised project implementation schedule to accommodate the Release 7.5 upgrade during the
first quarter of 1999
-- Continued data conversion and interface installation for implementation
--Installed and tested JetForm software for decentralized printing and forms design
--Developed specifications for personal data and demographic database conversions
--Implemented AutoSys (automated client/server job scheduling) and MQ series messaging
--Designed specifications and programming for payroll interfaces to financial systems
October-December 1999
--Developed large-scale conversion programs for transferring existing data to the new system
--Continued functional testing in all areas
--Course Catalogue module in production
--Admissions Pre-Application module in production
--Prepared for PeopleSoft version 7.5 release and installation, January 1999
January-March 1999
--Continued initial deployment specifications and user testing, data conversion
and interface installation for implementation
--Continued functional testing in all modules
--Met regularly with PeopleSoft and Cambridge Technology to oversee and
direct
upgrade strategy for PeopleSoft Version 7.5
--Installed Version 7.5 of the PeopleSoft system
--Installed and tested Version 7.5 database prepared at the PeopleSoft
upgrade lab
--Moved Undergraduate Admission Pre-Applicants and Course Catalog to Version
7.5 production
--Implemented Payroll for Version 7.5 production and began parallel testing
for first issue of ORION paychecks in May
--Completed implementation of Financial Aid 7.5
--Continued development of other modules in Version 7.5 for scheduled
implementation
--Completed requisition and negotiation process for interactive
voice-response/TouchTone
system to work with PeopleSoft
--Continued introductions to PeopleSoft system for academic and support
units
Activities for April-June 1999
--Continue planning, design and data conversion activities to prepare for system
implementation
--Complete and certify the results of the April payroll test run
--Begin ORION paycheck printing and distribution (biweekly 5/14; monthly 5/30)
and retire the current system
--Put Version 7.5 Financial Aid module into production
--Convert Admissions and Student Records data for current students
--Implement full Admissions processing
--Implement Spring 2000 Schedule of courses
--Install and implement IVR/Touch-tone system
--Continue campus-wide training program for functional users
--Continue to develop and test Web applications to reduce client workstation
requirements on campus and to permit WWW facilities for financial aid,
registration, personal information update, and human-resources
requirements
Updated 05/09/98
|